human data / guide · part 1
Designing a human-data pipeline
How I think about building a human-data operation from the beginning: what to pin down with the client, who to find and how to vet them, how to get experts working, and how to keep quality, time, and budget in view once they are. Part 1 of 2.
Numbers are illustrative examples.
01the start
A pipeline, from the very start
A human-data pipeline is everything between a client saying “we need data like this” and experts producing it at quality, on time, and on budget. Most of the work that decides whether a project goes well happens before anyone submits a task.
This is the general version of how I design one. It isn’t a story about a single client. For a specific time I had to change sourcing and vetting mid-project, read Vetting up front so QA isn’t the filter. For the hardest pipeline I’ve built, read Making agent traces readable enough to judge.
The contents on the left follow the stages in rough order: scope the work, find the people, set up, and run it. In practice they overlap. Set-up often starts while sourcing is still going. Delivery, security, and closing a project out are for Part 2.
02the data
Start with the data the client actually needs
The first question is what kind of data the client wants. “STEM” isn’t an answer you can staff against. Math at a bachelor’s level and math at a master’s level can be different jobs. So can marine biology and plant biology. Domain and difficulty both change who you need.
Early on I want to know the actual tasks, the expected outputs, and who is capable of producing them. Then the credential bar. Some clients require a master’s or a PhD. Some accept a bachelor’s. Some will take a skilled generalist with the right practical experience. That comes from the client and the project, and a degree alone still doesn’t prove someone can do the task.
Pick a domain first.
STEM. A category, not a staffing plan. Almost every planning question is still open.
- Who should we look for?
- What credentials does the client require?
- What tier of rate fits?
- What should the work sample test?
Example subjects, not a list of projects. A degree tier still isn’t proof someone can do the task. That’s what the work sample is for.
03the numbers
Four numbers before anything else
Four numbers set the shape of every human-data project: the client’s budget, the deadline or training-run date, the number of tasks, and the average handling time per task, or AHT. Together they decide the pace, the team size, and what the work can cost. Pin them down before anything else.
Timing decides how much room there is for sourcing, setup, onboarding, and calibration. Needing data in a week is a different project from a training run two months out. Volume times AHT gives the first view of the raw work. A hundred tasks at five minutes is 500 minutes. Ten thousand at twenty is a different operation entirely.
Same question, a 400× difference in raw work. These are task minutes, not calendar time, and not every cost. Rework and review come on top.
Raw work is only half of it. Add how many experts you have and how many hours a day each one really works, and the four numbers turn into a pace: how many tasks get done a day, how many days the job takes, how many experts it takes to hit the date, and what the expert hours cost against the budget.
- work hours = tasks × AHT ÷ 6010,000 × 20 ÷ 603,333.3 h
- tasks per day = experts × hours a day × 60 ÷ AHT50 × 4 × 60 ÷ 20600
- days to finish = work hours ÷ (experts × hours a day)3,333.3 ÷ (50 × 4)16.7 days
- experts needed = work hours ÷ (days × hours a day)3,333.3 ÷ (21 × 4), rounded up40
- expert cost = work hours × rate3,333.3 × $45$150,000
50 experts at 4 hours a day finish in about 16.7 days, inside the deadline and the budget.
Example inputs. This is first-pass production only: rework and review come on top, in the forecast below. Hours a day is what each expert actually works, not a full shift, and expert cost isn’t the client’s bill.
That arithmetic is only the start. Rework and review come later, in the forecast.
04rates
Rates decide who you can hire
Rates should be understood before the project moves. If they haven’t been agreed, that’s a conversation with the client now, not later. I’d price the actual work and the depth of expertise it needs: a math contributor, an advanced specialist, or a senior researcher. A degree helps describe the pool, but it doesn’t set the rate by itself.
The point is that the talent mix changes the economics. A budget that can’t attract the right people sinks the project before production starts. Put plainly: lower pay rates generally mean lower-quality data, because the experts who can do the work go elsewhere. The commercial side, how the company earns on billed hours, needs to be just as clear. A markup on an expert’s rate and a margin on the client’s bill aren’t the same number, so I’d pin down which one is in play before doing any billing math.
- math contributor · ~$40/hr · 70%
- advanced specialist · ~$60/hr · 20%
- senior researcher · ~$115/hr · 10%
Illustrative expert pay in USD. Actual rates vary by project, experience, and location.
05what good looks like
Define good before you scale
I want a golden task as early as possible: one known-good example of finished work. I ask what guidelines the client has written and whether they have a strong example. Sometimes they do. Sometimes we write the guidance ourselves. Even when the client has docs, the team usually still has to turn them into instructions experts can actually follow.
promptSolve for x: 3(x − 4) = 2x + 5
ideal responseExpand to 3x − 12 = 2x + 5, subtract 2x, add 12. x = 17. Check: 3(13) = 39 and 2(17) + 5 = 39.
why it’s goodEvery step shown, the answer checked, nothing extra.
06sourcing
Source for the project, not the category
Once the work is clear, sourcing is about the kind of person who fits it. There are two broad situations. Sometimes you build the pool by hand through LinkedIn, recruiting agencies, and other talent networks. That’s a grind, especially when the expertise is narrow and the clock is short.
Other times there’s already a network to search. The useful version holds each expert’s profile and resume alongside the transcript and video from an earlier AI interview. A general interview like that can be reused across projects. It helps you find people. It doesn’t tell you whether they can do this project’s work. The vetting step does that.
The interview is where a resume line turns into something you can use. Take a line like “Introduced new procedures that cut time to ship by 50%.” It reads well and says very little. Fifteen minutes of questions fills it in: what they changed, why it was better than what came before, how they measured the 50%, and what it meant for the company.
Those answers go into the record with the resume, so the network can be searched for what people have actually done, not just the words they chose. That’s how you can find someone who might do well on a project before they ever join it.
2 of 5 resumes contain those words. Keyword matches, not what anyone did.
Process improvement consultant for operations and support teams.
Backend-leaning engineer who likes fixing slow processes.
Analyst supporting operations teams.
Python backend engineer.
QA engineer for mobile and web.
Made-up profiles and answers. Open anyone to see the full record. The keyword search matches words as you type. The interview search asks Jev, a small AI model, how well each record fits your words. If it can’t be reached, a hand-tagged offline match fills in. It shows the difference, not a particular search method.
07top of funnel
Plan for far more people than you need
The starting pool is called the top of funnel, or TOF. The team you end up with and the number of people you reach out to are very different numbers. To fill around 50 seats, you might reach out to as many as 2,000.
People don’t respond. Some never apply. Some don’t meet the requirements. Some look right and then struggle with the work sample. A few raise integrity or security concerns. The plan has to absorb all of that between first contact and someone qualified and available.
50on the team
1,950who don’t get there, for reasons like:
- Don’t answer the offer
- Never apply
- Experience doesn’t meet the requirements
- Look right on paper, struggle on the work sample
- Integrity or security concerns
An illustrative example, not a conversion rate or a formula. There’s no split between the reasons because I don’t have one, and not every drop-off is a red flag.
08vetting
Make vetting look like the work
I want a short exercise built from something the expert would actually meet on the project. Depending on the task, that’s anywhere from about ten minutes to an hour. It can be a form with a few task-like questions, or a recorded session with camera, mic, and screen on, so you can see how someone works and how long it takes. A recording gives you more to look at. It doesn’t prove anything by itself.
How you judge it depends on the work. If there’s a right answer, compare against a known-good one. If the work leans on preference or judgment, like a lot of writing, a single answer key helps less. Then I’d look at prior work or give a prompt and assess what comes back, which takes judgment and is harder to automate.
Pay depends on the pool. With a wide generalist pool, a sample can be unpaid. For scarce, senior specialists, once their profile and interview look strong, I’d pay for the sample whether or not they’re picked. They have other offers, and the project has to give them a reason to spend the time.
| the work | has a right answer | needs judgment |
|---|---|---|
| format | A short form with a few task-like questions | A prompt to respond to, or examples of past work |
| judged | Against a known-good answer | Against what the project values. Harder to automate |
| the pool | wide, generalist pool | scarce specialists |
|---|---|---|
| pay | Can be unpaid | Paid, picked or not. They have other offers |
- Either way Built from something they’d meet on the project. About ten minutes to an hour, set by the task.
- Optional A recorded session, camera, mic, and screen on, to see how they work. More to look at, not proof on its own.
09the platform
Build the place they’ll work
This is my favorite part: getting the environment ready. It overlaps with sourcing. Some of it starts early, and some only gets finished once the team is picked.
Client tasks usually arrive as a CSV. We load them into a custom platform or a tool like Airtable, which I’ve built in a lot. A structured, sheet-like layer sits underneath. On top is something friendlier: a form-like view where an expert sees the task, copies what they need, annotates, and enters their response.
id,input,noteT-001,"Factor x² − 5x + 6",show each stepT-002,"Solve 2x + 7 = 19",check the answerT-003,"Simplify (x² − 9)/(x − 3)",state any restriction
| id | input | response |
|---|---|---|
| T-001 | Factor x² − 5x + 6 | — |
| T-002 | Solve 2x + 7 = 19 | — |
| T-003 | Simplify (x² − 9)/(x − 3) | — |
Factor x² − 5x + 6
note: show each step
Submit10onboarding
Onboarding, and a kickoff that’s paid
Human-data projects generally have two layers of docs. One is a reusable FAQ, often company-wide: system requirements, setting up Slack, how and when payment works, which time tracker to use. It’s written once, so project managers aren’t retyping it. The other is project-specific guidance: how to do these tasks, with the client’s golden examples, in Notion or a Google Doc. That guide is what gets spun up fresh each time a project kicks off.
Then setup. Experts get a company account, usually Google Workspace, plus time tracking and payment details. In the workflow I’m describing, everyone also gets a background check. Checks take time, so deciding on the team early keeps them from becoming the bottleneck right before the start.
When it’s ready, I get as many experts as possible on a kickoff call. I share my screen, walk through the task, and take questions live. Kickoff counts as paid onboarding, so time tracking is set up before the call.
- Monday 1team pickedFAQ sentbackground checks start
- Tueday 2work accounts createdpayment details in
- Wedday 3time tracking set upproject guide shared
- Thuday 4background checks still running
- Friday 5background checks still running
- Monday 6checks clear
- Tueday 7everyone set up, waiting for the date
- Wedday 8paid kickoff callplanned kickoff
- Thuday 9
- Friday 10
Picked early: the background checks clear with time to spare, and the paid kickoff happens on the planned day.
Illustrative business days, not measured. The background check is the slowest step, and check times vary. I’ve seen US and Canada checks come back faster than other regions, but that’s an observation, not a promise. Time tracking is set up before kickoff so the call is paid.
11first work
Cap the first work, then calibrate
After kickoff, everyone starts on real, paid project tasks, with a cap. Around one to three hours if they’re hourly, or one or two tasks if they’re paid per task. It’s a quality gate, but not a test batch. The cap is there so nobody piles up a lot of work before someone has looked at it.
We review that first work against the rubric, which might have three checks or fourteen. I want quality in the high 90s as soon as possible. That’s the target. First tasks are often weaker because people are still learning the guidance, and that’s what this stage is for.
Feedback goes straight to the expert. Where the workflow allows, the task goes back for a redo, and the redo has to pass before more work opens up. If the same issues come back, I’d rather get on a one-on-one call than send the same note again. Often it’s one or two points of guidance they haven’t understood. And if it still doesn’t improve, nobody is surprised, because everyone joined on a trial and knew the bar.
- Capped first work: 1–3 hours, or 1–2 tasks
- Review against the rubricissues found
- Written feedback
- Redo, checked against the guidancepasses
- One-on-one call
- Redo after the call
- More work opens up
Everyone hears the quality bar on day one, so offboarding is never a surprise. The caps and the number of chances are examples to fit to the task, not fixed settings.
12ongoing qa
From every expert to spot checks
At the start I check every single expert’s work. Once I have a confident read on each person, ongoing QA can shift to random spot checks across the pool to watch the health of the data as a whole.
That doesn’t mean I stop tracking people. I still want to know who passes on their first submission and who is consistently strong. That record is what I use to pick reviewers and team leads: the people doing the best, most aligned work. It isn’t only for spotting who’s struggling.
- reviewed, passed
- reviewed, needed a fix
- not reviewed
A made-up pool to show the shape, not a sampling rate. Spot checks don’t replace tracking each person.
13tracking
Run the project on data
Project management here runs on numbers. I track tasks submitted per day to see how fast we’re moving toward the goal. AHT ties throughput to the timeline and, with what experts are paid, to where the budget will land.
Made-up numbers. A slow start is normal while people calibrate.
14forecast
Forecast: the work, the rework, the review
The forecast I build is the initial task work, plus an allowance for rework, plus review time. Take 100 tasks at 20 minutes each. That’s 2,000 minutes, or 33 hours and 20 minutes, before anything goes wrong.
I like to assume at least 20% on top for errors, rework, and resubmissions. On this example that’s 400 more minutes, for 40 hours. That 20% is a time allowance, not a claim that one in five tasks fails.
Review is the piece you often can’t know at the start. You get a real baseline once reviews begin. Reviewing is usually a fraction of the production time, because the reviewer is checking work rather than creating it. A 20-minute task might take about five minutes to review. An hour-long task might take ten to twenty. A deep review might take about half as long as the task. Some clients also expect QA to happen in-house and haven’t budgeted for expert reviewers, which is part of why I move strong experts into that role when I can.
| production | 100 × 20 min | 2,000 min |
| rework allowance | 2,000 × 20% | 400 min |
| review | baseline comes once reviews start | ? |
| subtotal, before review | 2,400 min · 40h |
The allowance is extra time for errors, rework, and resubmissions. It isn’t a prediction that 20% of tasks fail. Review time and how much gets reviewed are separate inputs: five minutes on every task and five minutes on a spot check are different workloads.
The aim is to come in under budget. Total minutes still aren’t a schedule, though. You need staffing and availability to turn effort into calendar time.
15part 2
Where Part 2 picks up
This is deliberately half the story. Part 2 will get into what happens after the work is flowing:
- Who makes the call when evaluators disagree on a vetting result.
- How client changes turn into new guidance, rubric versions, and retraining.
- What a quality percentage actually measures on a given project.
- How spot checks are chosen, and when they widen after a problem.
- How the forecast changes when the real AHT differs from the estimate.
- Final delivery, client acceptance, permissions, and offboarding.
Until then, for one real project end to end, from the client’s example to delivery and what it did to first-pass acceptance, read Vetting up front so QA isn’t the filter.